Education - School Building cost

Posted in Education

School Building cost


S.N

Description

Quqntity

Units

Rates

Amounts Rs

01

Earthwork in Excavation

10469.00

Cu.ft

5.00

52345.00

02

Earth Back filling

13259.00

Sq.ft

3.00

39777.00

03

Flat brick soiling

5046.00

Sq.ft

25.00

126150.00

04

P.C.C

1665.42

Cu.ft

205.00

341411.10

05

R.C,C

6185.98

Cu.ft

225.00

1391845.50

06

Reinforcement

21650.93

Kg

100.00

2165095.00

07

Form work

      15351

Sq.ft

30.00

460530.00

08

Brick Work

9223.00

Cu.ft

165.00

1521795.00

09

Telia tile flooring

9791.10

Sq.ft

65.00

636421.50

10

Cement Skirting

1478.40

Sq.ft

22.00

32524.80

11

Plastering on wall, Ceiling

1478.40

Sq.ft

30.00

547041.00

12

Liun Plaster

7920.00

Sq.ft

12.00

95040.00

13

Wall Paints

18235.00

Sq.ft

13.00

237055.00

14

Enamel Paint

3489.00

Sq.ft

11.00

38379.00

15

Wooden Railing

175.00

Sq.ft

450.00

78750.00

16

Wooden handrailing

18.00

R.ft

475.00

8550.00

17

Wood Work for Frame

248.20

Cu.ft

1600.00

397120.00

18

Wooden Roof with Thatch

3686.00

Sq.ft

400.00

486000.00

19

Glazing window

1620.00

Sq.ft

300.00

486000.00

20

Flush Door Shuttering

672.00

Sq.ft

500.00

336000.00

21

Ceramic tile

850.00

Sq.ft

85.00

72250.00

22

Tiolet   2 rooms for B and G

2 Nos

 

70.000.00

70.000.00

 

Total in Nepali Rupees

 

 

10608477.90